Servicing the entire Sunshine Coast from Caboolture to Gympie
Fruit Shop – Maroochydore
Case Study
Brief
Engaged by the landlord to provide up to date assessment and report on current condition of equipment and systems within tenancy after 2-3 years out of operation.
In-tern, engaged to replace several complete systems and return the site to full operation
Details
Supplied and installed a new 28kw Coldroom system including 50m of new pipework and insulation
Decommissioned and disposed of all unrequired refrigeration, mechanical and electrical equipment
Supply and installation of multiple split system air conditioning units
Replacement of 25kw compressor in the existing packaged air conditioning unit
Retro fit of existing air conditioning ductwork to suit new tenancy layouts
Outcome
Customer was able to move in and initiate fit out before schedule with all systems operational as required